Luxcara starts construction of hydrogen hub

Published by , Editorial Assistant
Global Hydrogen Review,


Luxcara has begun construction of the Hamburg Green Hydrogen Hub (HGHH): Hamburg's First Mayor Dr Peter Tschentscher laid the official foundation stone for the construction of the 100 MW electrolyser at the site of the former Moorburg power plant.

Together with Environment Senator, Katharina Fegebank, Economics Senator, Dr Melanie Leonhard, and representatives of the two project partners Luxcara and Hamburger Energiewerke, he placed a time capsule in the foundation stone on site. The HGHH project plans to start commercial operations in the second half of 2027. Around 10 000 tpy of green hydrogen are set to be produced in Moorburg in future. The HGHH project is thus making an important contribution to the decarbonisation of the port and industry.

Dr Peter Tschentscher, First Mayor of the Free and Hanseatic City of Hamburg, said: "The construction of the Green Hydrogen Hub in Moorburg is an important project for the energy transition in Hamburg. The production of green hydrogen is a future-oriented technology that can significantly reduce CO2 emissions in industry and other sectors. Thanks to the wind energy from northern Germany, its connection to the supra-regional hydrogen network, and innovative industrial companies, Hamburg offers the best conditions for ramping up the H2 economy. I wish Hamburger Energiewerke, Luxcara, and everyone involved in the project every success and all the best for the construction of the 100 MW electrolyser!"

Dr Melanie Leonhard, Senator of the Hamburg Ministry of Economics and Innovation, added: “The industrial heart of our city beats in the port – and this is precisely where we are helping to ensure that hydrogen will be produced in the future for the climate-neutral energy generation of tomorrow. The switch from fossil gas to hydrogen is an important step in making industrial processes possible even as we strive to achieve our climate goals. The electrolyser in Moorburg is therefore part of the solution for making decarbonisation a reality in Hamburg – not just as a distant plan, but in very concrete terms.”

Dr Alexandra Bernstorff, Managing Partner Luxcara, stated: “The Hamburg Green Hydrogen Hub is more than just an energy project. It proves that green hydrogen is an investable asset today and that a climate-friendly energy transition can be implemented quickly. When politics, industry, and institutional investors work together reliably, a former coal-fired power plant can be transformed into a competitive, climate-neutral industrial site for Hamburg and far beyond. This requires stable framework conditions and functioning markets so that projects are not just announced but actually built, as is the case with our HGHH project.”

Kirsten Fust, Spokesperson for the Management Board of Hamburger Energiewerke, commented: “We are getting serious in Hamburg and moving into the implementation phase. We believe in hydrogen technology and are demonstrating with our Hamburg solution that pioneering green hydrogen projects can be driven forward through local commitment. However, in order to continue, we need better framework conditions at EU level, particularly with regard to the strict definition of green electricity in the Delegated Act.”

The HGHH project received funding approval from the federal and state governments last summer. Since then, the main construction contracts have been signed. The electrolyser was ordered from Siemens Energy in September 2024.

At the same time, demolition work on the former Moorburg power plant continued. This work began in October 2023 to make room for the 100 MW electrolyser and the connection to the hydrogen network. In the summer of 2025, the HGHH project took over part of the construction site as planned and began initial preparatory construction work. The first step was to prepare the subsoil of the 16 000 m2 site for the construction of the electrolyser building. A total of 906 vibro-compaction columns made of gravel were installed in the ground for this purpose. The floor slab has now been concreted, and the structural engineering work has begun.

The building for the electrolyser and compressors is scheduled to be completed by the middle of 2026. The stacks, the heart of the electrolyser, will then be delivered. The electrolyser is based on proton exchange membrane (PEM) technology. This involves splitting water into its components, hydrogen and oxygen, by using electricity along a membrane in a closed cell. This technology is particularly well suited for operation with renewable energy due to its flexible operation.

The green hydrogen will later be made available to customers via the HH-WIN hydrogen distribution network and the trailer loading station, which is also planned.

Read the article online at: https://www.globalhydrogenreview.com/hydrogen/02122025/luxcara-starts-construction-of-hydrogen-hub/