Nel ASA industrialises Next Generation Pressurized Alkaline platform
Published by Oliver Kleinschmidt,
Deputy Editor
Global Hydrogen Review,
Nel ASA has announced that following a seven-year development programme, and a successful start-up and production of clean hydrogen on the Next Generation Pressurized Alkaline prototype, the company’s Board of Directors has taken the final investment decision (FID) to begin construction on up to 1 GW of production capacity for this technology platform in the Herøya facility, Norway. The project is supported by the EU Innovation Fund.
Development of the Next Generation Pressurized Alkaline system was initiated in 2018 and after rigorous testing of various smaller stacks, Nel has now completed full scale testing of the prototype at Herøya Industripark, Norway, validating market-leading system efficiency. The company expects to launch the system commercially in the 1H26 and be able to deliver at scale in 2027.
Building on 100 years of technology experience, Nel's Next Generation Pressurized Alkaline platform delivers a breakthrough in clean hydrogen economics, dramatically reducing system CAPEX and improving energy efficiency, driving down levelised cost of hydrogen (LCOH). This leap is expected to improve overall hydrogen production economics, and bridge critical funding gaps for hydrogen installations.
“Our new solution is extremely important for Nel as a company, but also for the clean hydrogen industry as a whole. A significantly improved levelised cost of hydrogen is expected to unlock business cases that were previously not viable without significant subsidies,” said Håkon Volldal, President and CEO of Nel.
The platform is based on a fully modularised, skid-based design where every module is pre-fabricated and factory-tested before shipment in standard container skids. This approach dramatically simplifies engineering, logistics, and installation and is expected to transform complex projects into streamlined product deliveries. The system is designed to operate reliably outdoors, where costs and deployment complexity are further reduced as no dedicated building construction is required.
Nel has been granted up to €135 million in support from the EU Innovation Fund to industrialise the Next Generation Pressurized Alkaline platform, enabling a total annual production output of 4 GW. This funding covers up to 60% of relevant CAPEX and operational costs related to industrialisation.
The initial 1 GW of production capacity is estimated at an investment of about NOK300 million before grants. The EU grant is milestone based and this investment decision is expected to unlock in excess of €10 million as a first payment. The CAPEX is expected to be incurred throughout 2026 and 2027. Overall, the CAPEX for this platform is significantly lower than for atmospheric alkaline production lines.
Following the commercialisation and industrialisation of the pressurised alkaline solution the company is looking into the book values of the two 500 MW atmospheric alkaline production lines currently idling at Herøya.
Read the article online at: https://www.globalhydrogenreview.com/hydrogen/15122025/nel-asa-industrialises-next-generation-pressurized-alkaline-platform/
You might also like
ITM Power secures two engineering contracts
ITM Power have been awarded two engineering contracts, one in Australia and one in Canada.